The Challenge: An engineering firm needed freeze protection for eight large contaminated water tanks at a waste remediation site in the northern U.S.
Our Solution: The temperatures were dropping and time was running out to get tank heaters on site to prevent freezing. We swung into action with several design proposals. The customer selected and ordered four re-circulating heater / control panel skid systems. However, they needed these systems designed, built and shipped within 2 weeks! To save time, the customer decided to use on site pumps and piping to connect and operate the systems, instead of incorporating this into the skid package.
The Results: Our employees worked overtime and on the weekend to get approval drawings to the customer within two days. The units were constructed and functionally tested prior to shipment within the customer's required two week window.